The nation’s largest electrical grid operator has approved a new process for adding power plants to the sprawling transmission system it manages, including a two-year pause on reviewing and potentially approving some 1,200 projects, mostly solar power, that are part of a controversial backlog.
PJM Interconnection operates a competitive market for wholesale electricity in all or part of 13 states and the District of Columbia, from Virginia to northern Illinois. Its plan is the result of work over the past year by PJM and what it calls its stakeholders, according to a press release from PJM. They include electric utilities, electric transmission owners, state and consumer interests, and solar and wind developers.
“These changes represent a landmark accomplishment for PJM stakeholders and staff that establishes a better process to handle the unprecedented influx of generation interconnection requests and is critical to clearing the backlog of projects,” said PJM President and CEO Manu Asthana.
PJM remains committed to a strategy of “decarbonization policies while preserving reliability and cost-effectiveness,” Asthana said.
But the backlog, and a two-year pause on so many projects with the potential for even longer delays on new proposals, has frustrated a number of renewable energy developers.
In January, an outspoken Adam Edelen, a former Kentucky state auditor who runs a company working to bring solar projects and jobs to ailing coal communities in Appalachia, said he was concerned that “the kink in the system” was helping to delay effective climate policy in the United States. “The planet does not have time for a delay,” he said at the time.
Approval delays were putting solar developers in a financial bind and calling into question the Biden administration’s goal of having a carbon-free electricity grid in just 13 years, he cautioned.
Edelen late Thursday afternoon said he was still reviewing PJM’s announcement, which went out on Thursday.
“The current situation is preventing clean energy projects from coming online and is unsustainable,” said Kat Burnham, a principal of Advanced Energy Economy, a trade group for clean energy businesses that has expressed frustration with the situation. “While the reforms aren’t perfect, the updated process will help mitigate the project backlog. Any further delays would be worse for advanced energy projects and America’s clean energy transition.”
A PJM spokesman, Jeffrey Shields, said PJM would send its plan to the Federal Energy Regulatory Commission in May. FERC has 60 days to act on the plan, or it could not act and the plan would go into effect, Shields said.
Over the last four years, PJM officials have said they have experienced a fundamental shift in the number and type of energy projects seeking to be added to a grid, each needing careful study to ensure reliability. It used to be that PJM would see fewer, but larger, fossil fuel proposals. Now, they are seeing a larger number of smaller, largely renewable energy projects.
In all, there are about 2,500 projects awaiting action by the grid operator, which is based in Valley Forge, Pennsylvania, outside Philadelphia.
PJM has put forward a two-phased solution.
A new approval process will put projects that are the readiest for construction at the front of the line, and discourage those that might be more speculative or that have not secured all their financing.
Then, an interim period will put a two-year delay on about 1,250 projects in their queue—close to half of the total—and defer the review of new projects until the fourth quarter of 2025, with final decisions on those coming as late as the end of 2027.
Shields said that during the two-year transition, PJM will continue to work on more than 1,200 projects, which include more than 100,000 megawatts of renewable energy. “There is no shortage of renewables poised to come online,” he said.
The backlog, caused in part by the explosion of interest in solar energy, varies by state. Earlier this year, there were hundreds of projects waiting for review in states like Pennsylvania and Virginia, and dozens in states like Kentucky and West Virginia.
The Pennsylvania Energy Office was still reviewing the plan, said its spokesman, Jamar Thrasher, on Thursday.
“We support the changes PJM is implementing to create a more efficient and effective process, which will allow for the timely interconnection of generation to the PJM grid while ensuring reliability,” said Tammy Ridout, spokeswoman for the Ohio-based utility AEP.
“These improvements are critical to handle the influx of interconnection requests we have seen in recent years and will see for the foreseeable future,” said Ken Seiler, PJM vice president of planning, in a written statement. “This plan represents a real compromise among many different interests to get renewable and other projects through the queue as fast as possible and give developers a clearer picture of their costs and timelines.”
veryGood! (35)
Related
- Where will Elmo go? HBO moves away from 'Sesame Street'
- Walmart Yodeling Kid Mason Ramsey Is All Grown Up at 2024 ACM Awards
- Trump will campaign in Minnesota after attending his son Barron’s graduation
- National BBQ Day: See if your favorite barbecue spot made it on Yelp's top 100 list
- Trump invites nearly all federal workers to quit now, get paid through September
- Experts say coral reef bleaching near record level globally because of ‘crazy’ ocean heat
- Chris Pratt Speaks Out on Death of His Stunt Double Tony McFarr at 47
- A fiery tanker crash and hazmat spill shuts down Interstate 70 near Denver
- The Grammy nominee you need to hear: Esperanza Spalding
- Kim’s sister denies North Korea has supplied weapons to Russia
Ranking
- Could your smelly farts help science?
- Who plays Colin, Eloise and Penelope in 'Bridgerton'? See the full Season 3 cast
- They survived Maui's deadly wildfires. Now many are suffering from food insecurity and deteriorating health.
- California’s water tunnel to cost $20 billion. State officials say the benefits are worth it
- Backstage at New York's Jingle Ball with Jimmy Fallon, 'Queer Eye' and Meghan Trainor
- UAW’s push to unionize factories in South faces latest test in vote at 2 Mercedes plants in Alabama
- Kelsea Ballerini Channels Kate Hudson in How to Lose a Guy in 10 Days During 2024 ACM Awards
- Psychedelic therapy and workers’ rights bills fail to advance in California’s tough budget year
Recommendation
Toyota to invest $922 million to build a new paint facility at its Kentucky complex
US Navy flagship carrier USS Ronald Reagan leaves its Japan home port after nearly 9 years
How we uncovered former police guns that were used in crimes
UN resolution to commemorate the Srebrenica genocide in Bosnia sparks opposition from Serbs
Jamie Foxx reps say actor was hit in face by a glass at birthday dinner, needed stitches
Chargers schedule release video takes jab at Harrison Butker after kicker's comments on women
Nissan data breach exposed Social Security numbers of thousands of employees
LA County unleashes sterile mosquitoes to control the population. Here's how it works.